02/09/2022 --------------AirPermits IMS - PROJECT RECORD -------------------------------------------------------

Project#: 320169 Status: COMPLETE
Project Administrative Name: TRINIDAD GAS PROCESSING PLANT
Project Technical Name: TRINIDAD GAS PROCESSING PLANT

PROJECT ACTIONS

Permit Action Type Permit Type Received Date Permit Status Renewal Date Action Status Complete Date
9041A AMEND CONSTRUCT 09/14/2020 ISSUED 11/19/2020 COMPLETE 07/20/2021
9041A RENEWAL CONSTRUCT 09/14/2020 ISSUED 07/20/2031 COMPLETE 07/20/2021

Assigned Staff:
REVIEWR1_2:    HARVILLE , JENNIFER           REVIEW ENG:    RAY , MATTHEW          

MIDCOAST G & P (EAST TEXAS) L.P.
Midcoast G & P (East Texas) L.P.
CN603573817

Permit Information:
REGULATED ENTITY NUMBER: RN100226091
Permit Account Permittee Name County Region City State Location
9041A HM0011T TRINIDAD GAS PROCESSING PLANT HENDERSON REGION 05 - TYLER TRINIDAD TEXAS 795 LONE STAR RD


FEE:
Permit Action Type Reference Fee Receipt Number Fee Amount Paid Fee Refund Amount Fee Receipt Date Fee Payment Type
9041A AMEND 582EA000389 PI00510690 900.00 09/11/2020 ACH
9041A RENEWAL PI00510690 582EA000389888 1718.88 09/12/2020 ACH
9041A RENEWAL 582EA000389 PI00510690 900.00 0 09/11/2020 ACH
TRACKING ELEMENTS

TE Name     Start Date     Complete Date
POSTED TO EXECUTIVE DIRECTOR'S AGENDA (DATE)     07/08/2021
FINAL PACKAGE TO SECTION MANAGER FOR REVIEW (DATE)     07/08/2021
FINAL PACKAGE TO TEAM LEADER OR SUPERVISOR FOR REVIEW (DATE)     07/08/2021
WORKING DRAFT PERMIT REVIEW CYCLE     01/20/2021     07/08/2021
1ST NOTICE OCC COMPLETE (DATE)     11/17/2020
PUBLIC NOTICE COMMENT PERIOD (NSR 1ST NOTICE) - RENEWAL     10/15/2020     10/30/2020
LEGISLATORS NOTIFIED OF APPLICATION RECEIVED (DATE)     09/23/2020
AMENDED NOTICE FINALIZED AND SENT (DATE)     09/22/2020
COMPLIANCE HISTORY REVIEW COMPLETED (DATE)     09/21/2020
PROJECT RECEIVED BY ENGINEER (DATE)     09/18/2020
APIRT TRANSFERRED PROJECT TO TECHNICAL STAFF (DATE)     09/17/2020
LEGISLATORS NOTIFIED OF APPLICATION RECEIVED (DATE)     09/17/2020
SITE REVIEW RFC SENT TO REGION (DATE)     09/17/2020
PROJECT DECLARED ADMIN COMPLETE (DATE)     09/17/2020
COMPANY APPROVED DRAFT PUBLIC NOTICE (DATE)     09/16/2020
PUBLIC NOTICE DRAFT SENT TO COMPANY (DATE)     09/15/2020
APIRT RECEIVED PROJECT (DATE)     09/14/2020
ADMIN ADDITIONAL INFO CYCLE     09/14/2020     09/14/2020
APIRT PROJECT ASSIGNMENT REQUEST SENT     09/14/2020

Link Permit Link Permit Type Link Reason Link Program Interest
73139 PBR REFERENCED AIRNSR
Link Permit Link Permit Type Link Reason Link Program Interest
73139 PBR REFERENCED AIRNSR